NSTX-U 2nd Neutral Beam Relocation
Authors: N. Atnafu, M. Cropper, J. Edwards,
K. Gilton, T. Stevenson, M. Viola
Abstract: AThe NSTX-U project required doubling the Beam
Injection Power and extending pulse length. As a result, a second
neutral beam (BL2) was brought in from the old TFTR Test Cell. The
TFTR beam line had a Tritium contamination level of 120 million
dam/100 sq. cm. The overall weight of BL2 was 72 Ton and its
components weighed much as 40 Tons. Transporting the beam line
from the TFTR Test Cell to the NSTX-U Test Cell without spreading
contamination was a major priority. The components of BL2 were
disassembled in order to simplify transportation and be able to
decon all parts of the beam line. Decon reduced tenaciously held
tritium contamination within the beam line surfaces to
approximately two orders of magnitude. Some building structures
had to be removed including 9 Ton lintel shield blocks and HVAC
ducts to open up space for the beam line transportation. The 40
Ton NB Box was transported from the TFTR Test Cell to the NSTX-U
High Bay area by sliding it over air casters and was then moved
into the NSTX Test Cell by using the overhead crane to lift it
above the 22 ft shield wall. The Lid was then brought in and
placed inside the Box followed by other components including the
90" Flange, Magnet, Ion Dump, Exit Spool, TIV, Calorimeter,
platforms and Beamline Sources. Three High Voltage Enclosures
(HVE) were installed in the NSTX-U Test Cell and connected to the
beamline sources using transmission lines. At completion of the
2nd Neutral Beam relocation, a platform was built to provide
walkway to and from the 1st Neutral Beam and existing NSTX-U Test
Cell Platforms.
Submitted to: TOFE 2016, Philadelphia, PA
Download PPPL-5288 (pdf
1.9 MB 9 pp)
_________________________________________________________________________________________________