Control and Data Acquisition Upgrades for NSTX-U
Authors: W.M. Davis, G. J. Tchilinguirian, T.
Carroll, K. G. Erickson,
S. P. Gerhardt , P. Henderson, S. H.
Kampel,
P. Sichta, G. N. Zimmer
Abstract: The extensive NSTX Upgrade (NSTX-U)
Project includes major components which allow a doubling of the
toroidal field strength to 1 T, of the Neutral Beam heating power
to 12 MW, and the plasma current to 2 MA, and substantial
structural enhancements to withstand the increased electromagnetic
loads. The maximum pulse length will go from 1.5 to 5 seconds. The
larger and more complex forces on the coils will be protected by a
Digital Coil Protection System, which requires demanding real-time
data input rates, calculations and responses. The amount of
conventional digitized data for a given pulse is expected to
increase from 2.5 to 5 GB per second of pulse. 2-D Fast Camera
data is expected to go from 2.5 GB/pulse to 10, and another 2
GB/pulse is expected from new IR cameras. Our network capacity
will be increased by a factor of 10, with 10 Gb/s fibers used for
the major trunks. 32-core Linux systems will be used for several
functions, including between-shot data processing, MDSplus data
serving, between-shot EFIT analysis, real-time processing, and for
a new capability, between-shot TRANSP. Improvements to the MDSplus
events subsystem will be made through the use of both UDP and
TCP/IP based methods and the addition of a dedicated event server.
_________________________________________________________________________________________________
Submitted to: Fusion Engineering and Design
_________________________________________________________________________________________________
Download PPPL-5146 (pdf 2.3 MB 13pp)
_________________________________________________________________________________________________